Riverside Drive,Lochgilphead

A site start was achieved on 4th September 2023.  The contract period is 10 months, with contract completion expected in July 2024.

Baddens April 24

April 2024

Plots 1 & 2 first fix is progressing and plasterboard sheeting has commenced. The internal staircase has been installed and the blockwork is complete. Roughcasting is underway. Plots 3 & 4 roughcasting is complete and the scaffolding has been dropped, internal first fix installations are complete and taping and filling is progressing. Kitchen installation has started in plot 4. Plots 5 & 6 roughcasting is complete and scaffolding dropped, internal second fix electrical has commences and taping and filling is complete. Painter has applied mist coat and kitchens have been installed. Sanitary ware installation is progressing and internal doors, skirtings and facings have been installed in plot 5.

Baddens March 24

March 2024

Plots 1 & 2 roof tiling is complete, first fix is progressing and the sprinkler system first fix is complete. Blockwork is progressing and has reached first floor level. Plots 3 & 4 roughcasting is complete, internal first fix installations are progressing and plasterboard sheeting is progressing with taping/filling commenced. The internal stair case has been installed. Plots 5 & 6 roughcasting is complete along with the internal first fix installations and plasterboard sheeting. Taping and filling is progressing and the external doors have been installed along with the internal staircase.

Riverside Drive February update

February 2024

The sole plate has been installed at Plots 1 & 2 and the wall panels are progressing at plot 2. First fix is progressing in Plots 5 & 6. The roof battens have been installed at Plots 3 & 4 and counter battend and fire seperation will be complete next week to enable tiling to commence. The sprinkler system installers have run pipework through Plots 3, 4, 5 & 6. The timber kit is complete at Plots 1 & 2 and the roof is progressing with the trusses and underlay installed and battens progressing. The roof tiling has commenced at Plots 3 & 4 and the windows have been installed. The blockwork completed at Plots 5 & 6 and is ready to commence at Plots 3 & 4.

Riverside Drive January Update

January 2024

The joiners are progressing the insulation installation internally at 5 & 6. The ground floor wall panels of the kit have been installed at plots 3 & 4 and the scaffolding is being raised to accomodate kit completion. The floor slab has been formed at Plots 1 & 2 . The roof sarking has been installed at Plots 3 & 4 and the felt is progressing. The windows have been installed at plots 3 & 4. The blockwork is progressing at Plots 5 & 6 and first fix plumbing and electrical is also progressing.

Riverside Drive

December 2023

Plot 5 & 6 roof trusses have been installed and battens have been installed in preperation for tiling, The substructure upfill and drainage works are complete at plots 3 & 4 and the gas membrane has been installed. The steelwork is progressing and the floor slab will be poured on Friday 15th December. The substructure blockwork is complete at plots 1 & 2. The roof tiling has commenced at plots 5 & 6. The windows have been installed at plots 5 &6. The floor slab at plots 3 & 4 has been formed and the sole plate has been installed. The wall panels at plot 4 have commenced.

Riverside Drive November Update

November 2023

The foundations have been poured at Plots 1 & 2 which completes the six foundations. The substructure blockwork is nearing completion at Plots 3, 4, 5 & 6 and the weak mix cpncrete fill has been installed to cavity. The floor slab has been formed at Plots 5 & 6 and the kit erection has commenced. The scaffolding is going up around plots 5 & 6. The bricklayers are on site this week progressing with blockwork at plots 1 & 2, however progress has hampered by freezing conditions.

Riverside Drive January Update

October 2023

The foundations for plots 3 & 4 and 5 & 6 have been set out and the groundworks subcontractor has installed the shutering for the foundation at plots 5 & 6. Digger work is taking place at plots 1 & 2 to reduce the levels slightly.

Riverside Drive September Update

September 2023

The excavation work is complete. The stone infill is progressing with tippers running to the site throuout the day. The Roller is being used to compact the stone infill within the excavation.